Tyler Island Levee Failure- Emergency Work to Start Immediately

EMERGENCY RESPONSE: Dutra will be responding to the Tyler Island Levee Failure. Evacuations are in process with the immediate threat to locals, as well as multiple properties and businesses. Operation details are still evolving- with 24-7 barge loading permitted. Current expected project length is two weeks. We will keep you updated with more details as soon as they are available.

UPDATE 2/22/17: This work was completed on time, and without issue. The total hours of operation for this project totaled to 26 hours, with a total of 4 barges loaded.

If you have any questions or concerns, you can contact Aimi Dutra at (415) 307-1592.